Pothole repair progresses

Posted Jul 26, 2024 3:43 PM

Manhattan Public Works said although they had to pause summer #PotholeBlitz effort to work on other repair projects such as Casement Road and Fort Riley Boulevard, they plan to resume it later this summer when more materials become available.  The goal is to finish getting through all neighborhoods.

So far:

--7,295 potholes have been filled since May 14

--13,600 man-hours (18 people for 20 days at 8 hours per day

--129.7 tons of asphalt used in #AsphaltRepair so far