KDOT to begin re-opening westbound I-70 in Junction City

Posted Nov 11, 2024 9:00 PM
<br>

The contractor has scheduled to begin reopening WB I-70 through Junction City in Geary County.

Traffic will be reduced to one lane on EB & WB I-70 as the contractor works to finalize construction. Following the completion of Phase 2, I-70 is scheduled to fully reopen to unrestricted traffic in mid-late November.

The final phase of construction, Phase 3, is scheduled to begin in March 2025 and be completed by Dec. 2025.