USD 383 has reported via social media that work is continuing on different construction projects in the district.
* College Hill Early Learning Center framing is going up quickly
* Oliver Brown Elementary School is a few weeks behind schedule due to rain, but once the building pad is in, work will start on the footings.
* Anthony and Eisenhower Middle Schools have a gained a few additional weeks of construction due to school closure. The team is working on switching the library and offices areas (which would have been done this summer anyway). Lots of dirt work happening at both schools for the community center additions. (no photos included of middle school projects)
*Keith Noll Maintenance Center has a roof, walls, and electricity. Interior framing will start next week.