The City of Manhattan said that the Anderson Avenue reconstruction project will be ongoing this week. After completing curb and gutter repairs and complex base repairs last week, Shilling Construction Company Inc. will be installing the new asphalt overlay this week and into next week.
Shilling anticipates it will take 8 to 10 working days to complete all of the asphalt work, then permanent striping will occur on the new lanes.